Lab Build-Outs Start at the Lease: A Conversation with Project Manager, Michael Pabros

Most lab build-out surprises don’t start on the job site. They start before the lease is signed. In our recent guide to 2026 Life Science Lab Fit-Out Costs, we looked at what tenants should budget.

Labspace Directory spoke with Michael Pabros, Founder of a.i. Const PM about how to keep those numbers from growing. Michael is a CRE Associate and Project Development Manager at Lee & Associates in San Francisco, with 20 years of project management experience and more than 2 million square feet of Bay Area tenant improvements.

Our conversation covered building systems, fire department permitting, lease details, and how AI is changing project management for lab tenants.

1. How did you get into life science project management/tenant improvements?

My first lab project was in 2008, when I managed the build-out for Theravance at 901 Gateway Boulevard in South San Francisco. The project included a turnkey 2,000 SF vivarium, accredited by the Association for Assessment and Accreditation of Laboratory Animal Care International (AAALAC), alongside 15,000 SF of biology wet labs.


2. What are the most common surprises on timeline and budget, and how do you avoid them?

Two come to mind.

1. Building systems capacity. On one lab project, the existing HVAC, exhaust, electrical, and plumbing systems couldn’t support the proposed lab equipment. The marketing flyers and supporting documents listed the systems, but no one had field-verified their actual capacity, confirmed the load calculations, or checked that the equipment cycled and functioned correctly. After lease execution, the project required extensive coordination with the landlord, which caused significant schedule delays and unanticipated costs.

I avoid this by getting involved early, ideally before lease signing. We field-verify system capacities, confirm load calculations, and test equipment through its operating cycles. You would be surprised how much equipment fails to function properly after sitting idle for months.

2. Chemical storage quantities and control-area limits. Fire department requirements often trigger redesign, unexpected costs, and permitting delays.

I address this through early engagement with the fire prevention team. During preconstruction, we confirm lab classifications, chemical inventories, maximum allowable quantities, control-area limitations, and permitting requirements. I also build a working relationship with the fire department. Rather than simply submitting chemical inventories, we walk them through the overall business operation, laboratory workflows, and intended processes. Pick up the phone, introduce yourself and the team, and have the conversation.

When the fire prevention team understands the operation, they often identify compliant alternatives and practical solutions that reduce redesign, shorten permitting timelines, and control costs. You want them as a partner. If you just take a number and submit, you can fall into a vague review and permit process that sends you down a much longer path to approval.

The key in both cases is getting the right people involved before the lease is signed, rather than discovering these issues after the tenant is financially committed.


3. What should a first-time lab tenant understand before starting a build-out?

I have two pieces of advice.

First, know your site and know your lease. Once I land on a project, I prepare a lease abstract and review it with the project team and stakeholders. We calendar every milestone date so the team misses no deadlines.

Second, confirm the costs and fees associated with your build-out. Some work letters require tenants to fund overages before landlord reimbursement. Tenants also often overlook that rent commencement can occur before the lab is operational. On our projects, we build a responsibility matrix that identifies each cost as landlord-funded, TI-allowance-funded, or tenant-direct. We also confirm exclusions, fee caps, reimbursement deadlines, base-building conditions, and restoration obligations in the work letter, including the specific sunrise and sunset clause dates.


4. What sets your approach apart from other project management firms?

I bring 20 years of project management experience and more than 2 million square feet of Bay Area tenant improvements across a wide range of asset types. That experience lets me speak confidently about lab design, constructability, budgeting, and execution.

I review the lease and work letter as closely as the construction documents, because some of the most significant client savings are in the details of those agreements. I walk the sites, drive the meetings, challenge assumptions, and make informed decisions to protect the schedule and budget.

I approach every project as a problem to solve. There are always opportunities to identify risks, eliminate unnecessary costs, and negotiate better outcomes. Turning those into measurable savings is where I add the most value for my clients.


5. How are artificial intelligence and automation changing project and program management, and how are you using them?

On my projects, AI reviews pay applications, change orders, schedules, and meeting notes, and flags issues. I verify every flag, walk the site, drive the meetings, and make the decisions. Clients get faster document review with senior experience behind every decision. Learn more at constpm.ai.


Key Takeaways

Pabros’s perspective highlights an important distinction in lab build-outs: the costliest problems are rarely construction problems. They are lease, building-systems, and permitting issues that surface after a tenant is already committed.

For tenants, the best protection comes early. Verifying building systems, understanding chemical storage limits, and knowing which costs are landlord-funded, allowance-funded, or tenant-direct before signing can prevent the redesigns, delays, and budget overruns that follow. Reviewing the lease and work letter as closely as the construction documents, and bringing in the fire prevention team early, helps keep a project on schedule and on budget.